Guidance Notes :  Unless specified otherwise the following criteria are  to be used.
a.
All beaming is to be installed as shown in Standard Detail BF09.
b.
All Bow Flex ties are to be installed as shown in Standard Detail BO01 or BO02 as appropriate.
c.
Beam to be tied to a minimum of two separate joists either side of the stairwell.
STAIRWELL
METHOD STATEMENT
BF
14
Reinforce Bowing Cavity Walls Around Stairwells